Friday 20 September 2013

Plaster, Insulation and solar hot water panels

Ok plaster has been started and i think due to be completed by the end of the week. Meeting this week for the septic tank and all going along nicely.

Spa 

Main Bedroom

Lounge room ceiling

Study WIR

Laundry

Solar Hot Wate

Back of paddock

Back of house

Living Area

Fire

Living Area

Phone Line

Front

Saturday 14 September 2013

Air Con, Fireplace (almost), baths and more

Has been a busy two days by the look of it with the addition of quite a few things for 3 days of work. The electrical wiring has been almost completed and aircon / wood heater have been semi installed.

I think we are still on track to have the plaster on by the end of the week.

Aerial Point for Electricity

Meter Box

Half finished fireplace

Spa

Web of Aircon Ducting

Pantry / Data Cabinet Location

Bath

Lounge through the main bedroom to ensuite 

Back of house

New aircon

Close-up of aircon

Giant back sliding door



Tuesday 10 September 2013

Roof completed

OK there has been some progress on the house and after a few weeks of very little it seems to be happening all at once. We are scheduled for plumper, air con, heater, electrician, plaster, telephone and a few other things in the next few weeks.